§ 3922. Payment of retainage to subcontractors.

In the absence of sufficient reason, within 20 days of the receipt of payment by the contractor, the contractor shall pay all subcontractors with which it has contracted their earned share of the payment the contractor received.

Disclaimer: These codes may not be the most recent version. Pennsylvania may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.