Go to Previous Versions
of
this Section
2025 Oregon Revised Statutes
Volume : 19 - Utilities, Vehicle Code, Watercraft, Aviation
Chapter 758 - Utility Rights of Way and Territory Allocation; Cogeneration
Section 758.415 - Enforceability of contract approved by commission; conditions for approval.
Universal Citation:
OR Rev Stat § 758.415 (2025)
Learn more
This media-neutral citation is based
on the American Association of Law Libraries Universal Citation Guide and is not
necessarily the official citation.
Notwithstanding any other provisions of law, a contract entered into pursuant to ORS 758.410, when approved by the Public Utility Commission as provided in ORS 758.420 to 758.475, shall be valid and enforceable; provided, that the commission shall approve such a contract only if the commission finds, after a hearing as provided in ORS 758.420 to 758.475, that the contract will eliminate or avoid unnecessary duplicating facilities, and will promote the efficient and economic use and development and the safety of operation of the utility systems of the parties to the contract, while providing adequate and reasonable service to all territories and customers affected thereby. [Formerly 757.620]
Disclaimer: These codes may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.