Section 279C.660 - Compensation when contract terminated due to public interest.

Universal Citation: OR Rev Stat § 279C.660 (2019)

When a public contract is terminated by mutual agreement, provision shall be made for the payment of compensation to the contractor. In addition to a reasonable amount of compensation for preparatory work and for all costs and expenses arising out of termination, the amount to be paid to the contractor:

(1) Shall be determined on the basis of the contract price in the case of any fully completed separate item or portion of the work for which there is a separate or unit contract price; and

(2) May, with respect to any other work, be a percent of the contract price equal to the percentage of the work completed. [2003 c.794 §162]

Disclaimer: These codes may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.