2019 Oregon Revised Statutes
Volume : 07 - Public Facilities and Finance
Chapter 279C - Public Contracting - Public Improvements and Related Contracts
Section 279C.550 - "Retainage" defined.

Universal Citation: OR Rev Stat § 279C.550 (2019)

As used in ORS 279C.550 to 279C.570, "retainage" means the difference between the amount earned by a contractor on a public improvement contract and the amount paid on the contract by the contracting agency. [2003 c.794 §146; 2005 c.103 §32]
Disclaimer: These codes may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.