2017 Oregon Revised Statutes
Volume : 12 - Drugs and Alcohol, Fire Protection, Natural Resources
Chapter 517 - Mining and Mining Claims
Section 517.834 - Temporary operating permit; rules.

Universal Citation: OR Rev Stat § 517.834 (2017)

(1) Notwithstanding ORS 517.810 and 517.830, the State Department of Geology and Mineral Industries may issue a temporary operating permit to a person if:

(a) After consultation, the local jurisdiction with land use authority over the permitted site does not raise substantive objections to the issuance of the permit;

(b) All cooperating agencies approve of the permit issuance; and

(c) There is no objection from persons owning property adjacent to the permitted site.

(2) A temporary operating permit issued under this section is subject to reasonable limitations that may be prescribed by the department.

(3) Within 30 days after issuing the temporary operating permit, the operator shall:

(a) Comply with the bond and security requirements established by ORS 517.810;

(b) Pay any applicable fee pursuant to ORS 517.800; and

(c) Submit a reclamation plan to the department.

(4) The governing board of the department shall adopt rules governing the issuance of temporary operating permits. The rules shall include provisions:

(a) Ensuring opportunities for notice and comment by federal agencies;

(b) Specifying the terms of a temporary operating permit; and

(c) Establishing procedures for converting a temporary operating permit to a standard operating permit. [2005 c.34 §4; 2017 c.736 §14]

Disclaimer: These codes may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.