758.545 Electric utility required to make good faith effort to transmit energy; remedy.


OR Rev Stat § 758.545 (through Leg Sess 2011) What's This?

(1) If an electric utility fails to make a good faith effort to comply with a request from a qualifying facility to transmit energy or energy and capacity produced by the qualifying facility to another electric utility or to the Bonneville Power Administration, the electric utility shall purchase the qualifying facility s energy or energy and capacity at a price which is the higher of:

(a) The electric utility s avoided cost; or

(b) The index rate.

(2) As used in this section, good faith effort shall be demonstrated by the electric utility s publication of a generally applicable, reasonable policy of the electric utility to allow a qualifying facility to use the electric utility s transmission facilities on a cost-related basis. [1983 c.799 5]

Disclaimer: These codes may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.