2011 Oregon Revised Statutes
ORS Volume 13, Chapters 536 - 644
ORS Chapter 543a
543A.300 Decommissioning; rules.


OR Rev Stat § 543A.300 (through Leg Sess 2011) What's This?

(1) If any person operating a hydroelectric project fails to advise the Water Resources Department within 60 days of the time established in ORS 543A.030 or 543A.075, the Water Resources Commission may order the decommissioning of the project.

(2) The Water Resources Commission shall adopt by rule procedures for ordering a decommissioning of a project and standards for conducting a decommissioning in a manner that ensures the protection of the public health and safety and the environment. The rules shall include a provision for establishing a Hydroelectric Application Review Team for the project to coordinate the activities of all state agencies involved in the decommissioning process. [1997 c.449 30]

Disclaimer: These codes may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.