543A.100 Final application for water right; application for water quality certification.


OR Rev Stat § 543A.100 (through Leg Sess 2011) What's This?

Not less than two years before the expiration of the federal license for the project, the applicant shall submit the final application to reauthorize the water right and a request for certification under ORS 468B.040 and 33 U.S.C. 1341. The application submitted under this section shall be the same as the final application submitted to the Federal Energy Regulatory Commission for the new federal license for the project. [1997 c.449 20]

Disclaimer: These codes may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.