(A) An electric distribution utility subject to a final financing order shall file with the public utilities commission, at least annually, or more frequently as provided in the final financing order, a schedule applying the approved adjustment mechanism to the phase-in-recovery charges authorized under the final financing order, based on estimates of consumption for each customer class and other mathematical factors. The electric distribution utility shall submit with the schedule a request for approval to make the adjustments to the phase-in-recovery charges in accordance with the schedule.

(B) The commission's review of the request shall be limited to a determination of whether there is any mathematical error in the application of the adjustment mechanism to the phase-in-recovery charges, including the calculation of any proportionate charges allocated to governmental aggregation customers as directed in the final financing order.

(C) A request submitted under division (A) of this section shall be deemed approved, and the adjustments shall go into immediate effect, if not approved by the commission within sixty days after the request is submitted.

(D) No adjustment approved or deemed approved under this section shall in any way affect the irrevocability of the final financing order as specified in section 4928.235 of the Revised Code.

Disclaimer: These codes may not be the most recent version. Ohio may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.