§ 22C-5 - Late payments to bear interest.

Universal Citation: NC Gen Stat § 22C-5 (2020)

22C-5. Late payments to bear interest.

Should any periodic or final payment to a subcontractor be delayed by more than seven days after receipt of periodic or final payment by the contractor or subcontractor, the contractor or subcontractor shall pay his subcontractor interest, beginning on the eighth day, at the rate of one percent (1%) per month or a fraction thereof on such unpaid balance as may be due.

(1987 (Reg. Sess., 1988), c. 946.)


Disclaimer: These codes may not be the most recent version. North Carolina may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.