2006 New York Code - Remedies.



 
    §  756-b.  Remedies.  1.  (a)  If  any  interim  or final payment to a
  contractor is delayed beyond the due date established in  paragraph  (a)
  of  subdivision  three  of  section  seven  hundred  fifty-six-a of this
  article, the owner shall pay the contractor interest  beginning  on  the
  next  day at the rate of one percent per month or fraction of a month on
  the unpaid balance, or at a higher rate consistent with the construction
  contract.
    (b) Notwithstanding any contrary agreement, if any  interim  or  final
  payment to a subcontractor is delayed beyond the due date established in
  paragraph  (b) of subdivision three of section seven hundred fifty-six-a
  of  this  article  the  contractor  or  subcontractor  shall   pay   its
  subcontractor  interest,  beginning  on the next day, at the rate of one
  percent a month or fraction of a month on the unpaid balance,  or  at  a
  higher rate consistent with the construction contract.
    2.  (a)  (i)  If  an  owner  fails to approve or disapprove an invoice
  within the time limits established in subparagraph (i) of paragraph  (a)
  of subdivision two of section seven hundred fifty-six-a of this article,
  or  to  pay the contractor the undisputed invoice amount within the time
  limits provided by paragraph (a) of subdivision three of  section  seven
  hundred   fifty-six-a  of  this  article,  the  contractor  may  suspend
  contractually required  performance,  only  after  providing  the  owner
  written  notice  and an opportunity to cure consistent with subparagraph
  (ii) of this paragraph.
    (ii) A contractor intending to suspend performance on the construction
  contract for failure of the owner to make timely payments  or  approvals
  within  the  time limits provided by this article must provide the owner
  written notice at  least  ten  calendar  days  before  the  contractor's
  intended suspension. Such notice shall:
    (A)  inform the owner that payment for undisputed invoice amounts have
  not been received; and
    (B) state the intent of the  contractor  to  suspend  performance  for
  non-payment.
  If  after  the tenth calendar day following written notice the owner has
  not cured the deficiency, the contractor may suspend performance.
    (iii) A contractor shall not be deemed in breach of  the  construction
  contract for suspending performance pursuant to this section.
    (b)(i)  A subcontractor may suspend contractually required performance
  if any or all of the occurrences outlined in clauses (A), (B) and (C) of
  this subparagraph occur and only after providing written notice  and  an
  opportunity to cure consistent with subparagraph (ii) of this paragraph:
    (A)  If an owner fails to make timely payments for undisputed invoices
  within the time limits established by subdivision three of section seven
  hundred fifty-six-a of this article for the subcontractor's work and the
  contractor also fails to pay the subcontractor for the approved work;
    (B) If an owner pays the contractor within the time limits established
  by subdivision three  of  section  seven  hundred  fifty-six-a  of  this
  article  for undisputed invoices for work performed by the subcontractor
  but the contractor fails to make payment to the subcontractor within the
  time frames established by this article for the subcontractor's work;
    (C)  If  an  owner  fails  to  approve  or  disapprove  a  portion  of
  contractor's  invoice for work performed by the subcontractor within the
  time limits established in paragraph (a) of subdivision two  of  section
  seven hundred fifty-six-a of this article;
    (D)  If a contractor or subcontractor fails to approve or disapprove a
  subcontractor's invoice within the time limits established in  paragraph
  (b)  of  subdivision  three of section seven hundred fifty-six-a of this
  article; or
    (E) If an owner fails to approve portions of the contractors'  billing
  for   work  performed  by  the  subcontractor  within  the  time  limits
  established by this article and the reasons for such failure are not the
  fault of or directly related to the subcontractor's work.
    (ii)  A  subcontractor intending to suspend performance for failure to
  receive timely payments within the time limits established  pursuant  to
  this  article  must  provide  both  the owner and the contractor written
  notice at least ten calendar days before  the  subcontractor's  intended
  suspension. Such notice shall:
    (A)  inform  the  owner and the contractor that payment for undisputed
  billing amounts have not been received; and
    (B) state the intent of the  contractor  to  suspend  performance  for
  non-payment.
    If  after  the  tenth calendar day following written notice either the
  owner or the contractor has not cured the deficiency, the  subcontractor
  may suspend performance.
    (iii)   A   subcontractor  shall  not  be  deemed  in  breach  of  the
  construction  contract  for  suspending  performance  pursuant  to  this
  section.
    (iv)  (A)  A  contractor or subcontractor that suspends performance as
  provided in this section shall not be required to furnish further labor,
  materials or services until the contractor or subcontractor is paid  the
  undisputed  invoice amount at the time period for completion as provided
  in the construction contract. All of the time frames established  within
  the  construction  contract  of  a  contractor or subcontractor shall be
  extended for the length of time performance was  suspended.  Payment  of
  documented  actual  costs  incurred  for  re-mobilization resulting from
  suspension shall be negotiated between the parties.
    (B) In the event of suspension of a construction contract, as provided
  in this article, all materials, equipment, tools, construction equipment
  and machinery located  at  the  job  site  shall  remain  the  sole  and
  exclusive  property  of  the  contractor  or  subcontractor and shall be
  removed from the job site, if necessary, within a reasonable  period  of
  time.  Access  to the contractor's or subcontractor's property shall not
  be unreasonably withheld.

Disclaimer: These codes may not be the most recent version. New York may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.