2006 New York Code - Obligations.



 
    §  756-a.  Obligations.  Except as otherwise provided in this article,
  the terms and conditions of a construction contract shall supersede  the
  provisions  of  this  article  and  govern  the  conduct  of the parties
  thereto.
    1. Billing cycle. The parties  to  a  construction  contract  may,  by
  mutual  agreement,  establish  a  billing  cycle  for  the submission of
  invoices  requesting  payment  for  work   performed   pursuant   to   a
  construction  contract. In the absence of an agreement by the parties as
  to the billing cycle, the billing cycle  shall  be  the  calendar  month
  within which the work is performed.
    2.  Invoices.  (a) A contractor shall be entitled to invoice the owner
  for interim payments at the end of the billing cycle. A contractor shall
  be entitled to submit a final invoice  for  payment  in  full  upon  the
  performance of all the contractor's obligation under the contract.
    (i)  Upon  delivery  of  an  invoice  and  all  contractually required
  documentation, an owner shall approve or disapprove all or a portion  of
  such  invoice  within  twelve  business days. Owner approval of invoices
  shall not be unreasonably withheld nor shall  an  owner,  in  bad  faith
  disapprove  all  or  a  portion  of  an invoice. If an owner declines to
  approve an invoice or a portion thereof, it must  prepare  and  issue  a
  written  statement  describing  those  items in the invoice that are not
  approved. An owner may decline to approve an invoice or  portion  of  an
  invoice for:
    (1) Unsatisfactory or disputed job progress;
    (2) Defective construction work or material not remedied;
    (3) Disputed work materials;
    (4)   Failure   to  comply  with  other  material  provisions  of  the
  construction contract;
    (5) Failure of the  contractor  to  make  timely  payments  for  labor
  including  collectively  bargained fringe benefit contributions, payroll
  taxes and insurance, equipment and materials, damage to  the  owner,  or
  reasonable  evidence  that the construction contract cannot be completed
  for the unpaid balance of the construction contract sum; or
    (6) Failure of the owner's architect to certify payment for any or all
  of the reasons set forth in this section so  long  as  the  reasons  are
  included in the owner's written statement of disapproval.
    (ii)  Upon  delivery  of  an  invoice  and  all contractually required
  documentation, a contractor or subcontractor shall approve or disapprove
  all or a portion of such invoice within twelve business days. Contractor
  and  subcontractor  approval  of  invoices  shall  not  be  unreasonably
  withheld  nor  shall  a  contractor  or  subcontractor,  in  bad  faith,
  disapprove all or a portion of an invoice. Nothing in this section shall
  prohibit the contractor or subcontractor, at the time of application  to
  the  owner or contractor, from withholding such application to the owner
  or contractor for payment to the subcontractor or material supplier for:
    (1) Unsatisfactory or disputed job progress;
    (2) Defective construction work or material not remedied;
    (3) Disputed work;
    (4)  Failure  to  comply  with  other  material  provisions   of   the
  construction contract; or
    (5)  Failure  of  the  subcontractor to make timely payments for labor
  including collectively bargained fringe benefit  contributions;  payroll
  taxes  and  insurance,  equipment and materials, damage to contractor or
  another subcontractor or material supplier, or reasonable evidence  that
  the  subcontract  cannot  be  completed  for  the  unpaid balance of the
  subcontract sum.
    (b) Nothing in this subdivision shall authorize the withholding of  an
  application   to   the   owner  or  contractor  for  the  payment  to  a
  subcontractor or material supplier when due to a delay in  job  progress
  by  the  owner, contractor or another subcontractor or material supplier
  other than  the  applicant  or  applicant's  subcontractor  or  material
  supplier.
    3.  Payment.  (a)  The  owner's  payment of a contractor's interim and
  final invoices shall be made on the basis of a duly approved invoice  of
  work performed and the material supplied during the billing cycle.
    (i) Unless the provisions of this article provide otherwise, the owner
  shall  pay  the  contractor strictly in accordance with the terms of the
  construction contract.
    (ii) Unless otherwise agreed to by the parties, payment of an  interim
  or  final invoice shall be due from the owner not later than thirty days
  after approval of the invoice.
    (iii) If payment by the owner  is  contingent  upon  lender  approval,
  payment of a contractor's interim or final invoice or the amount of loan
  proceeds disbursed by the lender for payment of the contractor's interim
  or final invoice shall be due from the owner seven days after receipt by
  the  owner  of  good  funds except where the provisions of section seven
  hundred fifty-six-d of this article applies.
    (iv) An owner may withhold from an interim payment only an amount that
  is sufficient to pay the costs and expenses the owner reasonably expects
  to incur in order to cure the defect or correct any items set  forth  in
  writing pursuant to subparagraph (i) of paragraph (a) of subdivision two
  of  this  section,  or  in the alternative, to withhold an amount not to
  exceed the line item amount appearing in the agreed schedule  of  values
  together  with  any  change  orders, additions and/or deletions, if such
  schedule has been previously submitted, and/or an amount  sufficient  to
  cover  liquidated  damages  as established in an agreed upon schedule in
  the construction contract.
    (b) The contractor or  subcontractor's  payment  of  subcontractor  or
  material  supplier's interim or final invoice shall be made on the basis
  of a duly approved invoice of the work performed and materials  supplied
  during the billing cycle.
    (i)  Unless  the  provisions  of  this  article provide otherwise, the
  contractor or subcontractor shall  pay  the  subcontractor  strictly  in
  accordance with the terms of the construction contract. Performance by a
  subcontractor  in  accordance  with the provisions of its contract shall
  entitle  it  to  payment  from  the  party  with  which  it   contracts.
  Notwithstanding   this   article,  where  a  contractor  enters  into  a
  construction contract with a subcontractor  as  agent  for  a  disclosed
  owner,  the  payment  obligation  shall flow directly from the disclosed
  owner as principal to the subcontractor and through the agent.
    (ii) When  a  subcontractor  has  performed  in  accordance  with  the
  provisions of its construction contract, the contractor shall pay to the
  subcontractor,   and  each  subcontractor  shall  in  turn  pay  to  its
  subcontractors, the full or proportionate amount of funds received  from
  the  owner  for each subcontractor's work and materials based on work or
  services provided under the  construction  contract,  seven  days  after
  receipt  of  good  funds for each interim or final payment, provided all
  contractually required documentation and waivers are received.
    (iii) A contractor or subcontractor may withhold amounts received from
  an owner in connection with an interim payment due to a subcontractor or
  material supplier only such sums that are sufficient to pay  the  direct
  expenses  as  are reasonable to correct deficiencies identified pursuant
  to subparagraph (ii)  of  paragraph  (a)  of  subdivision  two  of  this
  section,  or in the alternative, to withhold an amount not to exceed the
  line item amount appearing in the agreed schedule  of  values,  together
  with any change order, additions or deletions, if such schedule has been
  previously  submitted,  and/or  an amount sufficient to cover liquidated
  damages as established in an agreed upon schedule  in  the  construction
  contract.
    (iv)  If a contractor, after submitting an invoice to an owner under a
  construction contract, but before making a payment to a subcontractor or
  material  supplier  for  the  subcontractor's  or  material   supplier's
  performance  covered by such invoice, discovers that all or a portion of
  the payment otherwise due to the subcontractor or material  supplier  is
  subject  to  withholding  from the subcontractor or material supplier in
  accordance with the construction contract and the conditions  set  forth
  in  subparagraph  (ii)  of  paragraph  (a)  of  subdivision  two of this
  section, then the contractor shall:
    (1) As soon as practicable upon ascertaining the cause giving rise  to
  a withholding, but prior to the due date for a subcontractor or material
  supplier  payment, furnish to the subcontractor or material supplier and
  the owner  written  notice  of  withholding  specifying  conditions  for
  withholding payment and identifying the amount to be withheld;
    (2)  Reduce the subcontractor's or material supplier's interim payment
  by an amount not to  exceed  the  amount  specified  in  the  notice  of
  withholding; and
    (3) Pay the subcontractor or material supplier amounts withheld within
  seven  days after correction of the identified subcontractor or material
  supplier  performance   deficiency   and   receipt   of   all   required
  documentation  and  waivers, unless the funds therefore must be obtained
  from the owner's  next  interim  payment  due  to  a  reduction  in  the
  contractor's  billing  directly  resulting  from  the subcontractor's or
  material supplier's performance deficiency identified in the  notice  of
  withholding.
    (c)  A  written notice of any withholding under this subdivision shall
  be issued to a subcontractor or material supplier specifying:
    (i) The amount to be withheld;
    (ii) The specific causes  for  withholding  under  the  terms  of  the
  construction contract and pursuant to this subdivision;
    (iii)  The remedial actions necessary to be taken by the subcontractor
  or material supplier  in  order  to  receive  payments  of  the  amounts
  withheld; and
    (iv) The documentation and waivers required.
    4.   Notice.  A  contractor  or  subcontractor  shall  disclose  to  a
  subcontractor, at the time the construction subcontract is entered into,
  the due date for receipt of payments to the contractor or  subcontractor
  from  the owner or the contractor as the case may be. If a contractor or
  subcontractor  fails  to  accurately  disclose  the  due   date   to   a
  subcontractor, the contractor or subcontractor shall be obligated to pay
  the  subcontractor  as though the due dates established in paragraph (a)
  of subdivision three of this section were met by the owner. In addition,
  upon written request of a subcontractor, the owner shall provide  notice
  to  such  subcontractor  within five days of making any interim or final
  payment to the contractor. The subcontractor's request shall  remain  in
  effect for the duration of the subcontractor's work on the project.

Disclaimer: These codes may not be the most recent version. New York may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.