Section 57-28-8 - Final payment.

Universal Citation:
NM Stat § 57-28-8 (2021)
Learn more This media-neutral citation is based on the American Association of Law Libraries Universal Citation Guide and is not necessarily the official citation.

Ten days after certification of completion, any amounts remaining due the contractor or subcontractor under the terms of the contract shall be paid upon the presentation of the following:

A. a properly executed release and duly certified voucher for payment;

B. a release, if required, of all claims and claims of lien against the owner arising under and by virtue of the contract other than such claims of the contractor, if any, as may be specifically excepted by the contractor or subcontractor from the operation of the release in stated amounts to be set forth in the release; and

C. proof of completion.

History: Laws 2001, ch. 68, § 8.

ANNOTATIONS

Effective dates. — Laws 2001, ch. 68 contained no effective date provision, but, pursuant to N.M. Const., art. IV, § 23, was effective June 15, 2001, 90 days after adjournment of the legislature.

Disclaimer: These codes may not be the most recent version. New Mexico may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.