2019 New Mexico Statutes
Chapter 3 - Municipalities
Article 24 - Electric Utility
Section 3-24-3 - Electric utility; municipality serving a governmental agency.

Universal Citation: NM Stat § 3-24-3 (2019)

Any municipality maintaining electric transmission lines more than five miles beyond the municipal boundary for the purpose of supplying electricity to the United States government, the state of New Mexico or any department or agency of these governments may:

A. acquire, by purchase, gift or other conveyance, any public utility system using such transmission line in providing service; and

B. acquire, construct, operate and maintain any electric utility system served by and contiguous to such transmission line, in conformity with:

(1) any franchise possessed by the public utility; or

(2) the consent and franchise from the governmental authority controlling the area to be served by the electric utility.

History: 1953 Comp., ยง 14-23-3, enacted by Laws 1965, ch. 300.

Disclaimer: These codes may not be the most recent version. New Mexico may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.