2011 New Mexico Statutes
Chapter 48: Liens and Mortgages
Article 2: Mechanics' and Materialmen's Liens, 48-2-1 through 48-2-19
Section 48-2-6: Time for filing lien claim; contents.


NM Stat § 48-2-6 (1996 through 1st Sess 50th Legis) What's This?

48-2-6. Time for filing lien claim; contents.

Every original contractor, within one hundred and twenty days after the completion of his contract, and every person, except the original contractor, desiring to claim a lien pursuant to Sections 48-2-1 through 48-2-19 NMSA 1978, must, within ninety days after the completion of any building, improvement or structure, or after the completion of the alteration or repair thereof, or the performance of any labor in a mining claim, file for record with the county clerk of the county in which such property or some part thereof is situated, a claim containing a statement of his demands, after deducting all just credits and offsets. The claim shall state the name of the owner or reputed owner, if known, and also the name of the person by whom he was employed, or to whom he furnished the materials, and shall include a statement of the terms, time given and the conditions of the contract, and also a description of the property to be charged with the lien, sufficient for identification. The claim must be verified by the oath of himself or of some other person.

Disclaimer: These codes may not be the most recent version. New Mexico may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.