    21-I:19-b Definitions. – In this subdivision:
    I. "Energy cost saving measure'' means any construction, improvement, repair, alteration, or betterment of any building or facility or any equipment, fixture, or furnishing to be added to or used in any building or facility that will be a cost effective energy-related project. This shall include any project that will lower energy or utility costs in connection with the operation or maintenance of such building or facility and will achieve energy cost savings sufficient to recover any project costs or incurred debt service within 20 years from the date of project implementation.
    II. "Energy performance contract'' means an agreement for the provision of energy services or equipment or both. This shall include, but shall not be limited to, energy conservation-enhancing projects in buildings and alternate energy technologies, in which a private sector person or company agrees to finance, design, construct, install, maintain, operate, or manage energy systems or equipment to improve the energy efficiency of, or produce energy in connection with, a state government agency or facility in exchange for a portion of the energy cost savings or specified revenues. The level of payments made would be contingent upon measured energy cost savings or energy production.
    III. "Positive cash flow financing'' means an agreement among an agency, a capital leasing firm, and a provider of design/build energy management services under which the leasing cost of the project, including all interest payments, is equal to or less than the energy cost the project avoids.
    IV. "Shared-savings contract'' means an agreement under which a private sector person or company undertakes to design, implement, install, operate, and maintain improvements to the agency's or municipality's procedures, equipment or facilities, and the agency or municipality agrees to pay a contractually specified amount of measured or estimated energy cost savings.
    V. "Date of project implementation'' means the expected date established in the energy performance contract that the construction, improvement, repair, alteration, or betterment is to be completed and become operational. If the energy performance contract includes more than one energy cost saving measure, the "date of project implementation'' may be alternatively defined by the contracting state agency or municipality to be the date that the last of the energy cost saving measures is expected to become operational.
    VI. "Demand response program'' means a program under which the state receives payment for voluntarily reducing electricity demand in response to grid instability as dictated by the regional independent system operator or in response to high wholesale electricity prices.

Source. 1993, 74:1. 1999, 225:6. 2000, 276:5. 2008, 166:2, eff. July 1, 2008. 2012, 149:3, eff. Aug. 6, 2012.


Disclaimer: These codes may not be the most recent version. New Hampshire may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.