View Our Newest Version Here

2021 Nevada Revised Statutes
Chapter 11 - Limitation of Actions
NRS 11.2055 - Actions for damages for injury or wrongful death caused by deficiency in construction of improvements to real property: Determination of date of substantial completion of improvement to real property.

Universal Citation:
NV Rev Stat § 11.2055 (2021)
Learn more This media-neutral citation is based on the American Association of Law Libraries Universal Citation Guide and is not necessarily the official citation.

1. Except as otherwise provided in subsection 2, for the purposes of this section and NRS 11.202, the date of substantial completion of an improvement to real property shall be deemed to be the date on which:

(a) The final building inspection of the improvement is conducted;

(b) A notice of completion is issued for the improvement; or

(c) A certificate of occupancy is issued for the improvement,

whichever occurs later.

2. If none of the events described in subsection 1 occurs, the date of substantial completion of an improvement to real property must be determined by the rules of the common law.

(Added to NRS by 1999, 1444; A 2015, 17)

Disclaimer: These codes may not be the most recent version. Nevada may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.