NRS 704.706 - Conversion of facility to allow firing by coal: Application for adjustment of rates; public hearing.

Universal Citation: NV Rev Stat § 704.706 (2020)

1. A public utility proposing to convert an existing facility in this state for the generation of electricity which is fired by gas or oil to a facility which is also capable of being fired by coal may apply to the Commission for an adjustment in its rates to permit its recovery of the cost of the conversion.

2. After receipt of such an application, the Commission shall hold a public hearing within 120 days to consider whether to authorize such an adjustment and, if authorized, the methods to be used to permit the recovery.

(Added to NRS by 1983, 752)

Disclaimer: These codes may not be the most recent version. Nevada may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.