2020 Nevada Revised Statutes
Chapter 704 - Regulation of Public Utilities Generally
NRS 704.370 - Issuance or refusal of certificate: Terms and conditions; hearing required for certain applications; power of Commission to dispense with hearing for certain applications.

Universal Citation: NV Rev Stat § 704.370 (2020)

1. The Commission shall have the power, after hearing, to issue or refuse such certificate of public convenience, or to issue it for the construction of a portion only of the contemplated line, plant or systems, or extension thereof, and may attach thereto such terms and conditions as, in its judgment, the public convenience and necessity may require.

2. Except as otherwise provide in subsection 3, the Commission, in its discretion and after investigation, may dispense with the hearing on the application if, upon the expiration of the time fixed in the notice thereof, no protest against the granting of the application has been filed by or on behalf of any interested person.

3. The Commission shall not dispense with the hearing on the application of an electric utility.

[Part 36 1/2:109:1919; A 1925, 243; 1947, 743; 1955, 407] — (NRS A 1963, 814; 2001, 350)

Disclaimer: These codes may not be the most recent version. Nevada may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.