To qualify to participate in the design and construction of a project for the Department, a design-build team must:

1. Except as otherwise provided in NRS 408.354, obtain a performance bond and payment bond as the Department may require;

2. Obtain insurance covering general liability and liability for errors and omissions;

3. Not have been found liable for breach of contract with respect to a previous project, other than a breach for legitimate cause;

4. Not have been disqualified from being awarded a contract pursuant to NRS 338.017, 338.13895, 338.1475 or 408.333; and

5. Ensure that the members of the design-build team possess the licenses and certificates required to carry out the functions of their respective professions within this state.

(Added to NRS by 1999, 3485; A 2001, 252, 639, 2022; 2003, 119)

Disclaimer: These codes may not be the most recent version. Nevada may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.