NRS 408.323 - Conditions for execution of work without contract; work resulting from disaster or emergency.

Universal Citation: NV Rev Stat § 408.323 (2019)

1. Whenever it can be justified by the Director that limited work or improvements can be done in a more economical or other satisfactory manner than by contract under NRS 408.327, the Director may, with the approval of the Board, execute such work or improvements with Department facilities and employees.

2. In the event of disaster or great emergency the Director may, with the approval of the Board, hire, employ or contract for such labor, materials and equipment as are in the Director’s opinion necessary to reroute, repair or replace any highway threatened or damaged by the emergency or disaster, and the provisions of NRS 408.327 and 408.367 do not apply.

(Added to NRS by 1957, 682; A 1979, 1771; 1987, 1805; 1989, 1303)

Disclaimer: These codes may not be the most recent version. Nevada may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.