2017 Nevada Revised Statutes
Chapter 338 - Public Works
NRS 338.570 - Contractor to provide notice concerning progress payments and retainage payments to certain subcontractors and suppliers.

Universal Citation: NV Rev Stat § 338.570 (2017)
Within 5 working days after a contractor receives a written request from a subcontractor or supplier of his or her subcontractor or supplier with respect to a subcontract which has not been fully performed, the contractor shall notify the subcontractor or supplier of his or her subcontractor or supplier in writing of the following:

1. The date the contractor made a specified progress payment or retainage payment to his or her subcontractor or supplier;

2. Whether the contractor has paid the entire amount of a specified progress payment or retainage payment to his or her subcontractor or supplier; and

3. The amount withheld by the contractor from a specified progress payment or retainage payment to his or her subcontractor or supplier, if any.

(Added to NRS by 1999, 1987)

Disclaimer: These codes may not be the most recent version. Nevada may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.