Cost of the project means all or a designated part of the cost of any project, including any incidental cost pertaining to the project. The cost of a project may include, without limitation, the costs of:

1. Surveys, audits, preliminary plans, other plans, specifications, estimates and other costs of preparations;

2. Appraising, printing, estimating, advice and services of engineers, architects, financial consultants, attorneys, clerical personnel and other agents and employees;

3. Publishing, posting, mailing and otherwise giving notice, filing or recording instruments, taking options and fees to banks;

4. Establishment of a reserve for contingencies;

5. Interest on bonds for any time which does not exceed the estimated period of construction plus 1 year, discounts on bonds, reserves for the payment of the principal of and interest on bonds, replacement expenses and other costs of issuing bonds;

6. Amending any resolution or other instrument authorizing the issuance of, or otherwise relating to, bonds for the project; and

7. Short-term financing and the expense of operation and maintenance of the project.

(Added to NRS by 2013, 1588)

Disclaimer: These codes may not be the most recent version. Nevada may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.