NRS 701B.865 - Procedure for selection and notification of participants; authorization to construct waterpower energy system; submission of incentive claim form and supporting information; determination of amount of incentive; withdrawal of participant; forfeiture of incentive. [Effective through December 31, 2021.]


NV Rev Stat § 701B.865 (2011) What's This?

1. An applicant who wishes to participate in the Waterpower Demonstration Program must submit an application to a utility.

2. After reviewing an application submitted pursuant to subsection 1 and ensuring that the applicant meets the qualifications and requirements to be eligible to participate in the Program, a utility may select the applicant for participation in the Program.

3. Not later than 30 days after the date on which the utility selects an applicant, the utility shall provide written notice of the selection to the applicant.

4. After the utility selects an applicant to participate in the Program, the utility may approve the waterpower energy system proposed by the applicant. Upon the utility s approval of the waterpower energy system:

(a) The utility shall provide to the applicant notice of the approval and the amount of incentive for which the waterpower energy system is eligible; and

(b) The applicant may construct the waterpower energy system.

5. Upon the completion of the construction of a waterpower energy system, the participant must submit to the utility an incentive claim form and any supporting information, including, without limitation, a verification of the cost of the project and a calculation of the expected system output.

6. Upon receipt of the incentive claim form and verification that the waterpower energy system is properly connected, the utility shall issue an incentive payment to the participant.

7. The amount of the incentive for which an applicant is eligible must be determined on the date on which the applicant is selected for participation in the Waterpower Demonstration Program, except that an applicant forfeits eligibility for that amount of incentive if the applicant withdraws from participation in the Program or does not complete the construction of the waterpower energy system within 12 months after the date on which the applicant is selected for participation in the Program. An applicant who forfeits eligibility for the incentive for which the applicant was originally determined to be eligible may become eligible for an incentive only on the date on which the applicant completes the construction of the waterpower energy system, and the amount of the incentive for which such an applicant is eligible must be determined on the date on which the applicant completes the construction of the waterpower energy system.

(Added to NRS by 2009, 1382; A 2011, 1944, 2563)

Disclaimer: These codes may not be the most recent version. Nevada may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.