NRS 11.2055 Actions for damages for injury or wrongful death caused by deficiency in construction of improvements to real property: Determination of date of substantial completion of improvement to real property.

NRS 11.2055 Actions for damages for injury or wrongful death caused by deficiency in construction of improvements to real property: Determination of date of substantial completion of improvement to real property.

1. Except as otherwise provided in subsection 2, for the purposes of NRS 11.202 to 11.206, inclusive, the date of substantial completion of an improvement to real property shall be deemed to be the date on which:

(a) The final building inspection of the improvement is conducted;

(b) A notice of completion is issued for the improvement; or

(c) A certificate of occupancy is issued for the improvement,

whichever occurs later.

2. If none of the events described in subsection 1 occurs, the date of substantial completion of an improvement to real property must be determined by the rules of the common law.

(Added to NRS by 1999, 1444)



Disclaimer: These codes may not be the most recent version. Nevada may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.