46-1645. Consulting board required; when; liability for costs.
When the safety and technical considerations pertaining to an application approval, an approval to operate, or the plans and specifications of a dam require it, or when requested in writing by the owner, the Chief Water Officer shall appoint a consulting board of three or more consultants to report to the Chief Water Officer on the safety features involved. The cost and expense of a consulting board, if appointed at the request of an owner, shall be paid by the owner.
Source
- Laws 2005, LB 335, § 45;
- Laws 2025, LB317, § 283.
- Operative Date: July 1, 2025
Disclaimer: These codes may not be the most recent version. Nebraska may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.