2022 Nebraska Revised Statutes
Chapter 18 - Cities and Villages; Laws Applicable to All
18-633 - Construction; cost; deposit; mandamus.

Universal Citation: NE Code § 18-633 (2022)

18-633. Construction; cost; deposit; mandamus.

When any viaduct or subway construction project has been agreed to or when the division of costs has been otherwise finally determined and when such proposal has been approved by a vote as provided in sections 18-617 to 18-636, the railroad company or companies affected shall within ten days' notice or demand deposit with the city treasurer or village treasurer the amount of its proportionate share. The district court is hereby given jurisdiction upon the application of the governing body of the city or village to compel such deposit by mandamus together with such penalties as may be found and deemed reasonable by the court.

Source

  • Laws 1949, c. 28, § 15, p. 109;
  • Laws 2021, LB163, § 63.

Disclaimer: These codes may not be the most recent version. Nebraska may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.