2020 Nebraska Revised Statutes
Chapter 37 - Game and Parks
37-1729 Commission; duties; powers.

Universal Citation: NE Code § 37-1729 (2020)

37-1729. Commission; duties; powers.

(1) Before the construction manager begins any construction services, the commission shall:

(a) Conduct an independent cost estimate for the project; and

(b) Conduct contract negotiations with the construction manager to develop a construction manager-general contractor contract for construction services.

(2) If the construction manager and the commission are unable to negotiate a contract, the commission may use other contract procurement processes as provided by law. Persons or organizations who submitted proposals but were unable to negotiate a contract with the commission shall be eligible to compete in the other contract procurement processes.

Source

  • Laws 2018, LB775, ยง 30.

Disclaimer: These codes may not be the most recent version. Nebraska may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.