31-748.01 Completion of contract; notice to district; objections; final payment; interest.

Universal Citation: NE Code § 31-748.01 (2020)

31-748.01. Completion of contract; notice to district; objections; final payment; interest.

If the contractor has furnished the district all required records and reports, the district shall after July 10, 1984, pay the contractor interest at the rate specified in section 39-1349, as such rate may from time to time be adjusted by the Legislature, on any contract amount retained and the final payment due the contractor beginning twenty days after completion of the work covered by the contract under section 31-748. The contractor shall notify the district in writing that the work has been completed and the district, within twenty days after receipt of such notice, shall give written notice to the contractor of any objections by the district to acceptance of the work.

Source

  • Laws 1963, c. 168, § 1, p. 583;
  • Laws 1969, c. 253, § 1, p. 923;
  • Laws 1984, LB 734, § 1.

Disclaimer: These codes may not be the most recent version. Nebraska may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.