39-1345.02 State highways; construction; contractor; liability.

NE Code § 39-1345.02 (2015) What's This?

39-1345.02. State highways; construction; contractor; liability.

A contractor shall not be held responsible, either during construction or after construction is completed, for damages which may result from or be due to inadequate, faulty, or insufficient design, plans, or specifications.

Source

  • Laws 1969, c. 310, ยง 2, p. 1115.

Annotations

  • This section provides an exception to section 39-1345.01 wherein, if contractors follow specifications provided, but those specifications are inadequate, faulty, or insufficient and so the traveling public still damages public works despite the implementation of the specifications, the contractors will not be liable for the damages to the actual construction project. The definition of damages found in section 39-1345.01 limiting damages to only those caused to an actual construction project also applies to the word "damages" as it appears in this section. Slagle v. J.P. Theisen & Sons, 251 Neb. 904, 560 N.W.2d 759 (1997).

Disclaimer: These codes may not be the most recent version. Nebraska may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.