70-1909 Electric supplier; limit on eminent domain.
70-1909.
Electric supplier; limit on eminent domain.An electric supplier as defined in section 70-1001.01 may agree to limit its exercise of the power of eminent domain to acquire a C-BED project which is a renewable energy generation facility producing electricity with wind and any related facilities if such electric supplier enters into a contract to purchase output from such facility for a term of ten years or more.
Source-
Laws 2007, LB629, ยง 9.
Disclaimer: These codes may not be the most recent version. Nebraska may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.