2006 Nebraska Revised Statutes - § 79-2011 — Contract proposals; evaluation; selection committee; duties.

Section 79-2011
Contract proposals; evaluation; selection committee; duties.

(1) In evaluating proposals in accordance with sections 79-2008 and 79-2010, the school district shall refer the proposals for recommendation to a selection committee. The selection committee shall be a group of at least five persons designated by the school district. Members of the selection committee shall include (a) members of the school board, (b) members of the school administration or staff, (c) the performance-criteria developer when evaluating proposals from design-builders under section 79-2008 or the school's architect or engineer when evaluating proposals from construction managers under section 79-2010, (d) any person having special expertise relevant to selection of a design-builder or construction manager under the Nebraska Schools Construction Alternatives Act, and (e) a resident of the school district other than an individual included in subdivisions (a) through (d) of this subsection. A member of the selection committee designated under subdivision (d) or (e) of this subsection shall not be employed by or have a financial or other interest in a design-builder or construction manager who has a proposal being evaluated and shall not be employed by the school district or the performance-criteria developer.

(2) The selection committee and the school district shall evaluate proposals taking into consideration the criteria enumerated in subdivisions (a) through (g) of this subsection with the maximum percentage of total points for evaluation which may be assigned to each criterion set forth following the criterion. The following criteria shall be evaluated, when applicable:

(a) The financial resources of the design-builder or construction manager to complete the project, ten percent;

(b) The ability of the proposed personnel of the design-builder or construction manager to perform, thirty percent;

(c) The character, integrity, reputation, judgment, experience, and efficiency of the design-builder or construction manager, thirty percent;

(d) The quality of performance on previous projects, thirty percent;

(e) The ability of the design-builder or construction manager to perform within the time specified, thirty percent;

(f) The previous and existing compliance of the design-builder or construction manager with laws relating to the contract, ten percent; and

(g) Such other information as may be secured having a bearing on the selection, twenty percent.

(3) The records of the selection committee in evaluating proposals and making recommendations shall be considered public records for purposes of section 84-712.01.


Source:
    Laws 2002, LB 391, § 11



~Reissue Revised Statutes of Nebraska

Disclaimer: These codes may not be the most recent version. Nebraska may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.