2021 Montana Code Annotated
Title 75. Environmental Protection
Chapter 8. Coal-Fired Generating Unit Remediation
Part 1. Coal-Fired Generating Unit Remediation Act
75-8-110. Water feasibility study

Universal Citation: MT Code § 75-8-110 (2021)

75-8-110. Water feasibility study. (1) On or before November 1, 2022, the owners of a coal-fired generating unit shall complete a water feasibility study in accordance with subsection (2). Costs of completing the study must be shared among the owners based on each owner's individual ownership interest in the coal-fired generating unit.

(2) The study required in subsection (1) must include:

(a) planning to ensure a local government attendant to a coal-fired generating unit is able to access the local government's water rights and related infrastructure in the event of closure of the coal-fired generating unit;

(b) an estimation of potential conveyance costs that could be incurred by a local government, for up to a 30-year timeline following closure of a facility; and

(c) recommendations, developed in consultation with the community attendant to a coal-fired generating unit, for meeting financial obligations necessary to ensure the affected local government is able to maintain its water supply and water rights.

(3) The study must be submitted to the department and included in remediation plans required in accordance with this part.

History: En. Sec. 1, Ch. 441, L. 2021.

Disclaimer: These codes may not be the most recent version. Montana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.