2019 Montana Code Annotated
Title 50. Health and Safety
Chapter 74. Boilers and Steam Engines
Part 2. Inspections
50-74-206. Boiler to be inspected prior to use -- duty of notification

Universal Citation: MT Code § 50-74-206 (2019)

50-74-206. Boiler to be inspected prior to use -- duty of notification. (1) The inspector of boilers must inspect all boilers and steam generators before the same are used.

(2) All persons who bring into this state for operation in this state any boiler or boilers must notify the department stating the number and kind of boilers and where they are to be located and operated in this state and must secure from the department a certificate of inspection before boilers are placed in operation except in the case of new boilers, which must be inspected within 90 days after they are put in use.

History: En. Sec. 554, Pol. C. 1895; re-en. Sec. 1643, Rev. C. 1907; amd. Sec. 5, Ch. 30, L. 1913; amd. Sec. 1, Ch. 32, L. 1919; re-en. Sec. 2714, R.C.M. 1921; re-en. Sec. 2714, R.C.M. 1935; amd. Sec. 2, Ch. 77, L. 1967; amd. Sec. 3, Ch. 225, L. 1971; amd. Sec. 26, Ch. 182, L. 1975; R.C.M. 1947, 69-1503(part); amd. Sec. 64, Ch. 613, L. 1989.

Disclaimer: These codes may not be the most recent version. Montana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.