Section 216E.11 IMPROVEMENT OF SITES AND ROUTES.

216E.11 IMPROVEMENT OF SITES AND ROUTES.
Utilities that have acquired a site or route in accordance with this chapter may proceed to
construct or improve the site or route for the intended purposes at any time, subject to section
216E.10, subdivision 2, provided that if the construction and improvement has not commenced
within four years after a permit for the site or route has been issued, then the utility must certify
to the commission that the site or route continues to meet the conditions upon which the site
or route permit was issued.
History: 1973 c 591 s 12; 1975 c 271 s 6; 1977 c 439 s 16; 2001 c 212 art 7 s 23; 2005
c 97 art 3 s 19

Disclaimer: These codes may not be the most recent version. Minnesota may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.