Chapter 21d - Massachusetts Hazardous Waste Facility Siting Act
Section 16 - Licenses and Permits; Time for Granting or Denial

Universal Citation: MA Gen L ch 21d § 16 (2021)

Section 16. No license or permit granted by a city or town shall be required for a hazardous waste facility which was not required on or before the effective date of this chapter by said city or town. All permits and licenses required for a hazardous waste facility in a city or town shall be granted or denied within sixty days after application for said permits and licenses by the developer, or twenty-one days after the establishment of a siting agreement pursuant to sections twelve and thirteen, whichever is the later.

Disclaimer: These codes may not be the most recent version. Massachusetts may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.