Section 62D Permit applications; time for agency determination

Section 62D. Agencies shall act on permit applications within ninety days following issue of notice of availability of the final environmental impact report, within ninety days following issue of notice of the determination that a report is not required, or ninety days following the permit application, whichever is latest, unless otherwise provided by law.

Disclaimer: These codes may not be the most recent version. Massachusetts may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.