2006 Massachusetts Code - Chapter 7 — Section 42H. Cost and pricing data for contract modifications.

Section 42H. The contractor shall submit, in accordance with regulations of the commissioner, cost and pricing data to be used when negotiating adjustments for change orders or other contract modifications. Such cost and pricing data shall be based on generally accepted accounting principles and be in conformity with the guidelines promulgated by the commissioner. Cost estimators employed within the division of capital asset management and maintenance shall review and evaluate cost and pricing data submitted by the contractor.

The contractor shall certify that, to the best of his knowledge and belief, the cost and pricing data submitted was accurate, complete, and current as of the date of submission. Any change order or contract modification under which a certificate is required shall contain a provision that the price to the commonwealth, including profit or fee, shall be adjusted to exclude any significant sums by which the commonwealth finds that such price was increased because the contractor-furnished cost or pricing data was inaccurate, incomplete, or not current as of the date of submission.

The provisions of section thirteen of chapter two hundred and fifty-eight of the General Laws, and the provisions of section sixty-seven A to section sixty-seven C, inclusive, of chapter two hundred and sixty-six, shall fully apply to the cost and pricing data certification requirements of this section.

Disclaimer: These codes may not be the most recent version. Massachusetts may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.