2006 Massachusetts Code - Chapter 7 — Section 42E. Definitions applicable to secs. 42E through 42I.

Section 42E. The words defined in this section shall have the meanings set forth below whenever they appear in sections forty-two E to forty-two I, inclusive.

“Change order” shall mean a written order not requiring the consent of the contractor, signed by the project manager and designated as an approved change order, directing the contractor to make changes in the work within the general scope of the contract, or, any written or oral order from the project manager which causes any change in the work, provided that the contractor gives the commonwealth written notice stating the date, circumstances, and source of the order and that the contractor regards the order as a change order.

“Contract modification” shall mean any written alteration in plans or specifications, period of performance, price, quantity, or any other provision of the contract accomplished by mutual action of the parties to the contract.

The project manager may at any time, subject to the requirements set forth herein and in section thirty-nine I of chapter thirty, order changes in the work within the general scope of the contract, including but not limited to changes: (a) in the plans and specifications (including drawings and designs); (b) in the method or manner of performance of the work; (c) in the commonwealth furnished facilities, equipment, materials, services or site; or (d) in the schedule for performance of the work. All such orders shall be written and designated to be change orders. All change orders or other contract modifications shall require the approval of the director when: (a) the cumulative cost of all previously approved increases in the contract price exceeds five per cent of the original contracted construction cost of the project, or such other percentage or dollar amount or criteria as designated by regulations of the commissioner; or (b) the preliminary estimate of the change in the contract price resulting from the change order or contract modification is $5,000 or more. The director may, after review of building projects for which the cumulative total of increases in the contract price has exceeded five per cent of the original contracted construction cost or such other percentage or dollar amount or criteria, direct the project manager as to those proposed changes, the preliminary estimated cost of which are under $5,000, that shall require the director’s approval.

The commissioner shall promulgate regulations governing the procedures for obtaining preliminary estimates and giving notice to the contractor as to the necessity of obtaining the director’s approval before any work pursuant to a change order or contract modification is commenced. Such procedures shall be designed so as to avoid delays in the progress of the project.

The project manager may delegate to the resident engineer, subject to approval by the director and notice to parties in interest, his authority to process and approve change orders when authorized to do so by regulations of the commissioner.

The provisions of section twenty A of chapter twenty-nine shall not apply to any change order request submitted and acted upon in accordance with sections forty-two E through forty-two I, inclusive, of this chapter.

Disclaimer: These codes may not be the most recent version. Massachusetts may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.