2017 Maryland Code
Environment
Title 5 - Water Resources
Subtitle 5 - Appropriation or Use of Waters, Reservoirs, and Dams
§ 5-510. Permit time limits to begin and complete work

Universal Citation: MD Env Code § 5-510 (2017)
  • (a) Time limit to begin work. -- Except for permits issued for the appropriation or use of water for agricultural purposes, the Department shall prescribe a time limit not exceeding 2 years from the grant of a permit, during which construction, reconstruction, or repair shall begin or appropriation or use of water shall be completed.
  • (b) Time limit to complete work. -- The Department shall prescribe a time limit, not more than 5 years from the grant of any permit, during which construction, reconstruction, or repair of reservoirs, dams, or waterway obstruction shall be completed.
  • (c) Extension for good cause. -- The Department may extend a permit-time limit for good cause shown.
Disclaimer: These codes may not be the most recent version. Maryland may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.