35-A §2508. Permits to specify time and place of opening

Universal Citation:
35-A ME Rev Stat § 2508 (2012 through 125th Legis)
Learn more This media-neutral citation is based on the American Association of Law Libraries Universal Citation Guide and is not necessarily the official citation.

Part 2: PUBLIC UTILITIES HEADING: PL 1987, C. 141, PT. A, §6 (NEW)

§2508. Permits to specify time and place of opening

Every permit for digging up and opening streets, roads and highways granted under this chapter must specify: [1987, c. 141, Pt. A, §6 (NEW).]

1. Time. The time during which the streets, roads or highways may remain open;

[ 1987, c. 141, Pt. A, §6 (NEW) .]

2. Place. The place where the opening may be made; and

[ 1987, c. 141, Pt. A, §6 (NEW) .]

3. Surface. The number of square yards of surface which may be disturbed.

[ 1987, c. 141, Pt. A, §6 (NEW) .]

SECTION HISTORY

1987, c. 141, §A6 (NEW).

Disclaimer: These codes may not be the most recent version. Maine may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.