35-A §4503. Filing certificate of public convenience
Universal Citation:
35-A ME Rev Stat § 4503 (2011 through 125th Legis)
Learn more
This media-neutral citation is based
on the American Association of Law Libraries Universal Citation Guide and is not
necessarily the official citation.
Part 4: GAS HEADING: PL 1987, C. 141, PT. A, §6 (NEW)
§4503. Filing certificate of public convenience
At least 30 days before beginning construction of an interstate natural gas pipeline within this State, the corporation shall file with the Secretary of State a certified copy of the certificate of public convenience and necessity issued to it under the Federal Natural Gas Act or, if the pipeline is intrastate, a certificate exhibiting the commission's authorization. [1987, c. 141, Pt. A, §6 (NEW).]
SECTION HISTORY
1987, c. 141, §A6 (NEW).
Disclaimer: These codes may not be the most recent version. Maine may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.