32 §15224. Installation of new elevators and tramways; fees
§15224. Installation of new elevators and tramways; fees
Detailed plans or specifications of each new or altered elevator or tramway must be submitted to and approved by the chief inspector before the construction may be started. Fees for examination of the plans or specifications must be set by the director under section 15225-A. [2001, c. 573, Pt. B, §28 (AMD); 2001, c. 573, Pt. B, §36 (AFF).]
SECTION HISTORY
1995, c. 560, §H14 (NEW). 1995, c. 560, §H17 (AFF). 1999, c. 386, §X19 (AMD). 2001, c. 573, §B28 (AMD). 2001, c. 573, §B36 (AFF).
Disclaimer: These codes may not be the most recent version. Maine may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.