RS 48:255.5 - Issuance of work orders and commencement of work

Universal Citation: LA Rev Stat § 48:255.5 (2018)

§255.5. Issuance of work orders and commencement of work

A.(1) Whenever the department enters into a contract for the construction, alteration, or repair of any public work, the department through its official representatives shall, before the issuance of any work order and before the commencement of any work, give notice of such contract, in writing, to all utility, communication, and public service companies and all public agencies and boards who furnish any utility, gas, water, electrical, communication, sewerage, or drainage services which may have underground pipes, cables, or any other underground installation which may be within the right-of-way where the public work is to be constructed, altered, or repaired. Said written notice shall require that the person, partnership, corporation, board, or agency so notified shall furnish to the department within a period of thirty days after receipt of notice, unless such time is extended by the department, a diagram or plat showing the location of such underground installations within the right-of-way, a copy of which shall be furnished by the department to the contractor before commencement of work under the contract. If such diagram or plat is not furnished within the time specified or any extension thereof granted by the department, the work order may be issued and the work commenced or the work order may be delayed.

(2) Should the diagram or plat not be furnished or the location of the underground cables, pipes, or other underground installations be inaccurately shown thereon, the department and the contractor shall be released from any responsibility in connection with their damage unless such damage is caused by the negligence of the department or contractor.

(3) If the work on the project is delayed due to the failure of the utility to furnish the plat or diagram required in this Section, the utility shall be liable for delays and cost escalations suffered by the contractor and the department.

B. This Section shall not relieve the department or contractor from the responsibility to give notice of intent to excavate or demolish to the regional notification center or centers serving the area in which the proposed work is to take place in order to be in compliance with the provisions of the "Louisiana Underground Utilities and Facilities Damage Prevention Law" as provided for in R.S. 40:1749.11 through 1749.22.

Acts 1997, No. 1112, §1, eff. July 14, 1997.

Disclaimer: These codes may not be the most recent version. Louisiana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.