16-1905 Suspension of performance, when.

Universal Citation: KS Stat § 16-1905 (2018)

16-1905.Suspension of performance, when. If any undisputed payment is not made within seven business days after the payment date established in a contract for public construction or in this act, the contractor and any subcontractors, regardless of tier, upon seven additional business days' written notice to the owner and, in the case of a subcontractor, written notice to the contractor, shall, without prejudice to any other available remedy, be entitled to suspend further performance until payment, including applicable interest, is made. The contract time for each contract affected by the suspension shall be extended appropriately and the contract sum for each affected contract shall be increased by the suspending party's reasonable costs of demobilization, delay and remobilization.

History: L. 2007, ch. 163, § 5; July 1.

Disclaimer: These codes may not be the most recent version. Kansas may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.