2015 Kansas Statutes
Chapter 66 PUBLIC UTILITIES
Article 12 MISCELLANEOUS PROVISIONS
66-1240 Construction of transmission and generation facilities; definitions.

KS Stat § 66-1240 (2015) What's This?

66-1240.Construction of transmission and generation facilities; definitions. As used in K.S.A. 2015 Supp. 66-1241 through 66-1244, and amendments thereto:

(a) "Appurtenances" means all substations, towers, poles and other structures and equipment necessary for the bulk transfer of electricity.

(b) "Bulk transfer" means the transport of a large amount of electricity at high voltage.

(c) "Commission" means the state corporation commission.

(d) "Construction or upgrade of an electric transmission line and appurtenances" means construction or upgrade of an electric transmission line and appurtenances to be used for the bulk transfer of 34.5 kilovolts or more of electricity.

(e) "Electric transmission line" means any line or extension of a line with an operating voltage of 34.5 kilovolts or more which is at least five miles in length and which is to be used for the bulk transfer of electricity.

History: L. 2004, ch. 120, § 1; July 1.

Disclaimer: These codes may not be the most recent version. Kansas may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.