2012 Kansas Statutes
Chapter 16 CONTRACTS AND PROMISES
Article 19 KANSAS FAIRNESS IN PUBLIC CONSTRUCTION CONTRACT ACT
Section 16-1907 Provisions waiving right to collect damages for delays, void, unenforceable.


KS Stat § 16-1907 (2012) What's This?

16-1907. Provisions waiving right to collect damages for delays, void, unenforceable. Any provision in a contract that purports to waive the rights of a party to the contract to collect damages for delays caused by another party to the contract shall be void, unenforceable and against public policy. This provision is not intended to create a contract between parties where a contract did not otherwise exist.

Disclaimer: These codes may not be the most recent version. Kansas may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.