572.33A

Liability of owner to general contractor — commercial construction.

1. An owner of a building, land, or improvement upon which a mechanic’s lien of a subcontractor may be posted is not required to pay the general contractor compensation for work done or material furnished for the building, land, or improvement until the expiration of ninety days after the completion of the building or improvement unless the general contractor furnishes to the owner one of the following:

a. Receipts and waivers of claims for mechanics’ liens, signed by all persons who furnished material or performed labor for the building, land, or improvement.

b. A good and sufficient bond to be approved by the owner, conditioned that the owner shall be held harmless from any loss which the owner may sustain by reason of the posting of mechanics’ liens by subcontractors.

2. This section applies only to commercial construction properties.

2012 Acts, ch 1105, §24, 27, 28; 2013 Acts, ch 99, §16; 2014 Acts, ch 1092, §128

Section takes effect January 1, 2013; mechanics’ liens filed prior to that date shall remain with the clerk of district court of the county in which the building, land, or improvement charged with the lien is situated; 2012 Acts, ch 1105, §27, 28

Disclaimer: These codes may not be the most recent version. Iowa may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.