2018 Iowa Code
Title XIV - PROPERTY
Chapter 572 - MECHANIC’S LIEN
Section 572.3 - Collateral security before completion of work.

Universal Citation: IA Code § 572.3 (2018)

572.3

Collateral security before completion of work.

No person shall be entitled to a mechanic’s lien who, at the time of making a contract for furnishing material or performing labor, or during the progress of the work, shall take any collateral security on such contract.

[C51, §1009; R60, §1845; C73, §2129; C97, §3088; C24, 27, 31, 35, 39, §10272; C46, 50, 54, 58, 62, 66, 71, 73, 75, 77, 79, 81, §572.3]

Disclaimer: These codes may not be the most recent version. Iowa may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.