2022 Indiana Code
Title 36. Local Government
Article 9. Transportation and Public Works
Chapter 40. County Funding of Sewage Disposal Systems
36-9-40-5. Estimate of Cost of System

Universal Citation: IN Code § 36-9-40-5 (2022)

Sec. 5. (a) The estimate of cost of the system required under section 4(4)(D) of this chapter may include all incidental, inspection, and engineering costs caused by the proposed construction. However, the estimate of the costs to be paid by special assessment may not include the following:

(1) Salaries and expenses of the necessary and regularly employed personnel of the engineering department of the county.

(2) Ordinary operating costs of the works board.

(b) If the works board determines that it is necessary to employ additional engineering services for construction of a particular system, the works board may include in the estimate of cost of the system required under section 4(4)(D) of this chapter the cost of the additional service actually performed in connection with the system.

As added by P.L.7-2002, SEC.1.

Disclaimer: These codes may not be the most recent version. Indiana may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.